On December 28th, 2012, Xiangshangang Bridge and its connection engineering was completed and opened to traffic. MBEC participated in the construction of the Project.
Since its commencement, the Project Administrative Department of MBEC has created an excellent achievement of prefabricating 11nos. 60m box girder segments within one month with merely 2 abutments and completed the prefabrication and erection of the 144nos. 60m box girder segments for Yunlong Flyover and the southern and northern approach bridges as well as the auxiliary surface construction in a safe and high quality manner, which laid a solid foundation for the timely completion and opening to traffic of the Bridge.